Articles in this section

Assign Quantities to Lots / Add Floating Quantities

Before you can assign quantities to lots, you must set up the Schedule Items register and create the Lots. Quantities with a Lot reference are known as Lot Quantities. In some cases, the quantities do not have a Lot reference and these are called Floating Quantities. 

Lot-based Quantities can be added from the Lot Register or Quantity Register. Floating Quantities can only be added from the Quantity Register.

Relevant Links:

Quantities Register

Add Schedule Items

Create Lots

 

Method 1: From the Lot Register ( Lot Quantities only)

 

1. Under Quality Assurance, select “Lot Register”.

Assign_Quantities_to_Lots_A1.png

 

2. Select the relevant Lot, click on the “Chain” icon on the right panel and then, the + sign next to “Quantities”.

Assign_Quantities_to_Lots_A2.png

 

3. Select the schedule item by clicking on it. Click “Next”.

Assign_Quantities_to_Lots_A3.png

 

4. Complete the followings :

  • Quantity – Enter the quantity manually (Alternatively, use the blue tabs to set the full schedule quantity or the remaining schedule quantity).
  • Preliminary – Select “Yes” only if the quantity entered is just an estimate and unconfirmed
  • Non-claimable and Reduced Payment Factor - refer to the article “Quantities Register” on how to apply these
  • Comments – Enter additional notes, if applicable

Click “Save and Exit” (To add more, click “Save and Add More”).  

Assign_Quantities_to_Lots_A4.png

 

5. You can now view the linked Quantity in the Lot register (Fig 5) and the Quantity register (Payment > Quantities).

Note: To unlink it, click on the “Cancel Link” icon next to Quantities.  

Fig 5

Assign_Quantities_to_Lots_A5.png

 

Method 2 – From the Quantity Register  ( Lot Quantities and Floating Quantities)

 

1. Under Payment, select “Quantities”

Assign_Quantities_to_Lots_B1.png

 

2. Select “New Quantity”

Assign_Quantities_to_Lots_B2.png

 

3. Complete the followings:

  • Type – Select the “Lot Quantity” or “Floating Quantity” 
  • Schedule Item – Select the schedule item from the dropdown list ( click on the “ >” next to the Heading to view and select the “Child” items)
  • Lot Test (for Lot Quantity only)– Select the Lot relating to the quantity
  • Description (for Floating Quantity only) – Add a description for the Floating Quantity  
  • Quantity – Enter the quantity manually (Alternatively, use the blue tabs to set the full schedule quantity or the remaining schedule quantity).
  • Preliminary - Select “Yes” if the quantity entered is just an estimate and unconfirmed
  • Non-claimable and Reduced Payment Factor -  refer to the article “Quantities Register” on how to apply these
  • Comments – Enter additional notes, if applicable

Click “Save”.

Assign_Quantities_to_Lots_B3.png

 

4. You can now view the added quantity in the Quantity register. For Lot Quantity, this can also be viewed in the Lot Register (refer to Method 1 - Step 5).  

Assign_Quantities_to_Lots_B4.png

 

 

 

Was this article helpful?
0 out of 0 found this helpful

More Resources

  • Watch Demo

    See how CivilPro supports smarter, more efficient Project and QA management

  • Contact Hours:

    8:30am - 5pm AEST Monday to Friday; Closed on Saturday and Sunday

  • Follow Us

    Stay connected - follow us on LinkedIn for updates, tips and announcements